Upcoming Work

CH3

Mass excavation continues throughout the entire footprint. Concrete operations are expected to mobilize in November. Erection of the tower cranes are anticipated to begin in December. Dry Utility work along 18th Street has started and is expected to be complete by end-December.

CH7/8

All required permits have been obtained. Full site mobilization has started with clearing and grading expected to start soon.